Re: MTO Production w/Procurement of Components

$
0
0


Hi ,

 

Your requirement can be met by available Planning Strategies. USe 50- Planning with final assembly( or 52) . this is what it does.

-Forecast/Planned independent requirements are valid as Demand/For MRP

- MRP run will generate Requirment/procurement proposal for whole BOM, but Forecased item(Top level) plan order(Type: VP) will not be able to convert to Prod order. It is instrument to create dependent requirement for child items.

-Sales order will consume forecast (Backward/forward/Consumption days etc)

-Sales order qty/date will drive next MRP run to generate plan order for Top level FG. It will delete VP plan order & replace with PE(Make -To -order ) plan order.'

- You can define Material master--> individual /collective indicator to 2  for  materials in BOM tree to delink procurement proposal/production orders for 1st level/2 level/ n level items.

- Finished goods stock will be tied to sales order when production completes

 

Hope this helps,

Jatin