I am unsure about the budget profile and the currency translation relevant settings.
Is it happening only at the IM level? Can you please co-relate the currency conversion rates at the WBSe Level as well. Once done; please compare the budget profile for IM and Project.
If not able to identify the cause of differences please raise the incident on SAP.