Hi,
This is more a conceptual question so please dont type up how to create an 03 and an 04 inspection lot.
- If I have 03 working perfectly and I control inspection during manufacturing then do I really need an 04 inspection lot ? What MICs can I park in the 04 inspection plan which I cannot park in the routing inspection operations ?
- Right now if I have more than one inspection operation in the production order, I can inspect the 2nd operation before I can inspect the 1st operation. How do I prevent that from happening ? I want to make sure that the 1st operation has to be in QMDA status before the 2nd operation can even be picked up for results recording.
Thanks