Our effort estimate is as follows please advise any changes for the same
SAP Componets | SAP Component Version information/upgradations | Resources Including Fuctiontional consultants | Estimated Duration | Remarks |
ECC | Technical implementation of ECC from 6.0 EhP3 to EhP7 | 3 | 6 months | |
Portal | Technical upgrade to Enterprise Portal 7.4 | 2 | 6 months | |
PI/XI | Technical upgrade of SAP PI and SLD from version 7.1 to 7.4 | 2 | 6 months | |
SLD | Upgrade of SLD | This should go Parallel with PI and Portal | ||
BW | Technical Upgrade of SAP BW from 7.01 to 7.4 | 2 | 6 months | |
NWDI | Upgrade of NWDI to version 7.4 | 2 months | Need to know the current version | |
BPC | BPC will require an upgrade to Version 10 | 1 | 2 months | |
BIA | H/W U/G @ 7.20 | |||
CRM | NA | |||
SRM | NA | |||
SAP Training | Master training system , Training clone systems | Need to understand more on requirements | ||
Nakisa | Need to understand more on requirements | |||
Netweaver Gateway 2.0 | Need to understand more on requirements | |||
Tangro | Need to understand more on requirements | |||
ABAP | ||||
SAP HR |