Re: PS Budget change from annual to Overall

$
0
0

Hi Jorge,

 

I don't think that it is technically possible to shift your assigned annual budget to overall level.

 

But do one try in testing system:

 

1) Create new WBS

 

2) Transfer your all actuals from old WBS to new ones wither via KB11N/CJ88.

 

3) But here commitment transfer is manual process, as we have to change manually account assignment elements in PRs/POs. There is no option for transferring commitments.

 

4) Assign pending works on new WBS and close/lock close ones.

 

Just give a try & check.

 

Also let others put their ideas on the matter.

 

 

Regards

Shishir