Re: Error in Commitment Check - see costing log

Hi experts,

 

     I'm facing the same problem except that I do have budget control active for the WBS elements. And the budget amount is Exactly the same as the PR amount.

The availability control usages are 80 , 90 , 100 % respectively for the actions1 , 2 , 3

 

Note: I have no user status assigned.

 

How do I open this costing log. from where !?

 

because it is not Menu Bar --> Extras --> Logs --> Cost Calculation .... log contains no values.

 

 

 

Please consider it a matter of high importance.

Thank you.