Re: Using Planned orders effectively in MRP

$
0
0

Hi,

Thanks for reply.

I tried with '2' Purchase requisitions in opening period but I observed that Planned order was not converted to PR after MRP run.

eg. Leadtime is 40 days

material is required on 31st sept. if I maintain Purchase requisitions in opening period =2 it wont convert into PR.

Instead keep as Planned order.