Quantcast
Channel: SCN: Message List
Viewing all articles
Browse latest Browse all 9091

Re: Production Order query

$
0
0

Hi Madhu,

 

If you are using production in alternative plant in that case you will have the planning plant in your production order. And good receipt will post to this plant.

In the material master for a material to be produced, special procurement key 'Production in another plant' need to be set.

Apart from that these is no other impact of this field.

 

Regards,

R.Brahmankar


Viewing all articles
Browse latest Browse all 9091

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>