Hello,
short update on SP1.
DS 1.5 SP1 is in upload process, visibility expected in next days.
initially planned for cal week 35.
we had to move by one week and the release (+ upload to service marketplace) has started yesterday. it is expected to have the external visibility today, at least for the smaller parts (client, nw, hana). bip can take a bit to upload, so it will probably appear on SMP.
if you plan an installation, try to have 1-2 weeks buffer between the planned RTC date and your implementation frame. it is only a planned date, all known issues from testing must be corrected, and this has priority over date, so in some cases the date can move a bit.
Karol